Escalators Installation

Task / Description Slow   Ave   Fast    Units
 Truss type, Overall Installation (excl arch finishes) 14.0  12.0  11.0   wks
 Truss type, Manufacture, test and deliver -   60.0  48.0   wks
 Truss type, Phase A assemble truss , position/level -   1.0  -    wks
 Truss type, Stop-Work for surrounding finishes 8.0  6.0  4.0   wks
 Truss type, Phase B decking and glazing etc -   5.0  -    wks
 Truss type, Phase C performance testing -   2.0  -    wks
 Truss type, Phase D full load testing -   2.0  -    wks
 Truss type, Phase E final test and inspection -   2.0  -    wks

 

Lift Installation

Task / Description Slow   Ave   Fast    Units
 Hydraulic Lift, Install 2 to 3 storeys -   3.0  -    wks/floor
 Hydraulic Lift, Install 4 storeys and above -   2.0  -    wks/floor
 Hydraulic Lift, Testing allow 2 wks plus -   1.0  -    day/floor
 Standard Lift, Manufacture, test and deliver -   12.0  -    wks
 Non-Standard Lift, Manufacture, test and deliver 75.0  65.0  52.0   wks

Choose Your Server

 Starting new projects and concepts is what makes us tick. So go on, get in touch. Drop us a line:

Sun Trees | Indigenous tree nursery, specimen tree trade, consulting tree architect and tree relocation

WaLS | architecture design | lampen-smith william

 
 
 

Power of Methvin

Register and start pricing immediately

Login Online