Task / Description Slow   Ave   Fast    Units
 FST Floating Track Slab, side restraints 9.6  -   -    m/day
 FST Floating Track Slab, resin pads 10.2  -   -    m/day
 FST Floating Track Slab, slab units 10.6  -   -    m/day
 PCBT - Pre-cast Concrete Block Track, in Bored Tunnels 17.1  41.0  -    m/day
 PCBT - Pre-cast Concrete Block Track, in Cut and Cover Tunnels -   35.0  -    m/day
 PCBT - Pre-cast Concrete Block Track, in Station Tunnels -   35.0  -    m/day
 IST - Isolated Slab Track, in Bored Tunnels -   20.0  -    m/day
 IST - Isolated Slab Track, in Cut and Cover Tunnels -   34.0  -    m/day
 IST - Isolated Slab Track, in Station -   29.0  -    m/day
 FST - Floating Slab Track, in Station 3.6  4.6  5.7   m/day
 Ballasted Track, in Mainline 57.0  71.0  115.0   m/day
 Ballasted Track, in Depot -   28.0  -    m/day
 Non-Ballasted Track, in Depot 8.5  12.8  17.4   m/day
 Embedded / Paved Track, in Depot -   71.0  -    m/day
 Heavy Maintenance / Train Wash Track, in Depot -   29.0  -    m/day
 Maintenance Pit, in Depot -   52.0  -    m/day
 Siding Trackwork, in Depot -   38.0  -    m/day

Choose Your Server

 Starting new projects and concepts is what makes us tick. So go on, get in touch. Drop us a line:

Sun Trees | Indigenous tree nursery, specimen tree trade, consulting tree architect and tree relocation

WaLS | architecture design | lampen-smith william

 
 
 

Power of Methvin

Register and start pricing immediately

Login Online