Planning and Estimating Production Rates

Task / Description Slow Ave Fast Units
Overall Installation for 100 persons or 50m2 - 3.0 - wks
Overall Installation for 500 persons or 150m2 - 5.0 - wks
Overall Installation for 1000 persons or 250m2 - 8.0 - wks
Install Ovens, friers and large mixers etc - 1.0 - mandays
Install Sinks, bain maries and washers etc - 2.0 - mandays