Planning and Estimating Production Rates

Task / Description Slow Ave Fast Units
Suspended Ceilings, office situations - 2.6 3.5 m2/hr
Suspended Ceilings, First Fix - 0.7 - m2/hr
Suspended Ceilings, Second Fix - 1.2 - m2/hr