Task / Description Slow   Ave   Fast    Units
 Vertical Glazed Lights, 6m x 2.5m -   14.5  -    m2/day
 Vertical Glazed Walls, large scale -   70.0  -    m2/day
 Clerestory Frame/Glazing, 3m x 4m -   28.0  -    m2/day
 Oriel Window Frame/Glazing, 4m x 2m -   35.0  -    m2/day
 Glazed Curtain Wall, First Fix -   1.2  -    m2/hr
 Glazed Curtain Wall, Second Fix -   1.1  -    m2/hr
 High Quality Glazed Curtain Walling -   25.0  -    m2/day