Planning and Estimating Production Rates

Task / Description Slow Ave Fast Units
Cable Installation, 1 cable laid in trench and protect - 6.2 - m/hr
Cable Installation, 2 cable laid in trench and protect - 5.6 - m/hr
Cable Installation, 5 cable laid in trench and protect - 4.3 - m/hr
Cable Installation, 7 cable laid in trench and protect - 3.7 - m/hr
Cable Installation, 8 cable laid in trench and protect - 3.5 - m/hr
Cable Installation, 2 cable laid in trench and protect, 100mm dia - 1.8 - m/hr
Cable Installation, 2 cable laid in trench and protect, 135mm dia - 1.6 - m/hr
Cable Installation, 3 cable laid in trench and protect, 100mm dia - 1.0 1.5 m/hr
Cable Installation, 6 cable laid in trench and protect, 100mm dia - 0.7 1.2 m/hr
Cable Installation, 4 cable laid in trench and protect, 150mm dia 0.7 1.2 3.1 m/hr
Cable Installation, 36 cable laid in trench and protect, 100mm dia - 0.2 - m/hr
Cable Installation, 10 cable laid in trench and protect, 100mm dia - 0.5 - m/hr
Cable Installation, 1 cable laid in trench and protect, 300mm dia - 1.3 - m/hr