Planning and Estimating Production Rates

Task / Description Slow Ave Fast Units
AC Install 2 no Service transformers, 6 men - 12.0 - days
AC Install 2 no Switchgear, 7 men - 12.0 - days
AC Install Associated Trays and ladders, 3 men 11.0 5.0 - days
AC Cable Terminations in Tx and SWG Rooms, 3 men 12.0 6.0 - days
DC Install Insulated Flooring in DC Room, 1 men - 5.0 - days
DC Install 1 set Rectifier Transformer and Rectifier, 7 men - 1.0 - days
DC Install Switchgear, 7 men - 10.0 - days
DC Primary Cable Terminations and Busduct, 18 men 12.0 9.0 - days
DC Secondary Cable Terminations and Connections, 9 men 12.0 6.0 - days
Trackside Cabling 33kV/Pilot Cables, 10 men 2,100.0 - - m run/day
Trackside Cabling Terminations, 6 men - 1.0 - days