Available work area < 60,000m2
m2
Working width < 40m
m
Location Rural = 1.0 Small City = 0.85 Big City = 0.75
%
Major pavement items Production Rate Unit
Lime-Treated Sub-grade 0 m2/d
Subbase production rate 0 m3/d
Basecource production rate 0 m3/d
Finishing basecource production rate 0 m2/d
Hot Mix Asphalt Base 0 Ton
Hot Mix Asphalt Surface 0 Ton
Concrete Paving 0 m2/d