Planning and Estimating Production Rates

Task / Description Slow Ave Fast Units
Setup small 2 hole system 10.0 8.0 6.0 days
Setup large 15 hole system - 21.0 - days
Calculate system times per pump - 2.5 - days/pump
Setup Recharge System - 3.5 - days/pump