Planning and Estimating Production Rates
/ Description | Slow | Ave | Fast | Units |
Hydraulic Excavator, 0.3m3 bucket, Sand/Soil | 6.7 | 8.4 | 9.9 | m3/hr |
Hydraulic Excavator, 0.3m3 bucket, Gravel Beds | 3.2 | 4.5 | 5.0 | m3/hr |
Hydraulic Excavator, 0.3m3 bucket, Clay/Chalk | 3.3 | 4.1 | 5.2 | m3/hr |
Hydraulic Excavator, 0.3m3 bucket, Hard Ground | 3.3 | 4.1 | 5.2 | m3/hr |
Hydraulic Excavator, 0.4m3 bucket, Sand/Soil | 8.2 | 10.0 | 11.7 | m3/hr |
Hydraulic Excavator, 0.4m3 bucket, Gravel Beds | 7.1 | 8.7 | 10.2 | m3/hr |
Hydraulic Excavator, 0.4m3 bucket, Clay/Chalk | 6.5 | 8.3 | 9.4 | m3/hr |
Hydraulic Excavator, 0.4m3 bucket, Hard Ground | 6.3 | 7.7 | 9.1 | m3/hr |
Hydraulic Excavator, 0.5m3 bucket, Sand/Soil | 12.2 | 13.3 | 15.4 | m3/hr |
Hydraulic Excavator, 0.5m3 bucket, Gravel Beds | 10.2 | 11.1 | 12.9 | m3/hr |
Hydraulic Excavator, 0.5m3 bucket, Clay/Chalk | 9.7 | 10.5 | 12.1 | m3/hr |
Hydraulic Excavator, 0.5m3 bucket, Hard Ground | 6.1 | 6.7 | 7.7 | m3/hr |
- Category: Excavation
- Hits: 22806
Planning and Estimating Production Rates
/ Description | Slow | Ave | Fast | Units |
Dozer, 0.8m3 bucket, Sand/Soil, pushed 5-50m to stockpile | 13.9 | 20.4 | 25.0 | m3/hr |
Dozer, 0.8m3 bucket, Sand/Soil, pushed 50-120m to stockpile | 7.6 | 9.5 | 12.6 | m3/hr |
Dozer, 0.8m3 bucket, Gravel, pushed 5-50m to stockpile | 14.2 | 20.4 | 25.6 | m3/hr |
Dozer, 0.8m3 bucket, Gravel, pushed 50-120m to stockpile | 7.6 | 10.2 | 12.8 | m3/hr |
Dozer, 0.8m3 bucket, Clay/Chalk, pushed 5-50m to stockpile | 12.7 | 18.4 | 23.2 | m3/hr |
Dozer, 0.8m3 bucket, Clay/Chalk, pushed 50-120m to stockpile | 6.9 | 8.9 | 11.6 | m3/hr |
Dozer, 0.8m3 bucket, Boulder Clay, pushed 5-50m to stockpile | 11.6 | 16.9 | 21.3 | m3/hr |
Dozer, 0.8m3 bucket, Boulder Clay, pushed 50-120m to stockpile | 6.3 | 8.2 | 10.4 | m3/hr |
Dozer, 1.2m3 bucket, Sand/Soil, pushed 5-50m to stockpile | 23.8 | 28.5 | 35.7 | m3/hr |
Dozer, 1.2m3 bucket, Sand/Soil, pushed 50-120m to stockpile | 16.7 | 18.5 | 20.4 | m3/hr |
Dozer, 1.2m3 bucket, Gravel, pushed 5-50m to stockpile | 25.0 | 32.0 | 37.0 | m3/hr |
Dozer, 1.2m3 bucket, Gravel, pushed 50-120m to stockpile | 17.2 | 19.3 | 21.2 | m3/hr |
Dozer, 1.2m3 bucket, Clay/Chalk, pushed 5-50m to stockpile | 21.7 | 27.5 | 33.3 | m3/hr |
Dozer, 1.2m3 bucket, Clay/Chalk, pushed 50-120m to stockpile | 15.1 | 16.9 | 18.8 | m3/hr |
Dozer, 1.2m3 bucket, Boulder Clay, pushed 5-50m to stockpile | 19.6 | 24.5 | 30.3 | m3/hr |
Dozer, 1.2m3 bucket, Boulder Clay, pushed 50-120m to stockpile | 13.7 | 15.9 | 17.5 | m3/hr |
Dozer, 0.6m3 bucket, 50-200m2, Sand/Soil | 18.6 | 28.5 | 38.5 | m3/hr |
Dozer, 0.6m3 bucket, over 200m2, Sand/Soil | 24.4 | 37.2 | 50.0 | m3/hr |
Dozer, 0.6m3 bucket, 50-200m2, Gravel | 18.9 | 28.6 | 38.4 | m3/hr |
Dozer, 0.6m3 bucket, over 200m2, Gravel | 24.2 | 37.2 | 50.0 | m3/hr |
Dozer, 0.6m3 bucket, 50-200m2, Hardcore | 15.8 | 23.5 | 31.2 | m3/hr |
Dozer, 0.6m3 bucket, over 200m2, Hardcore | 19.2 | 29.6 | 40.0 | m3/hr |
Dozer, 0.6m3 bucket, 50-200m2, Boulder Clay | 17.2 | 26.4 | 35.7 | m3/hr |
Dozer, 0.6m3 bucket, over 200m2, Boulder Clay | 22.2 | 33.8 | 45.4 | m3/hr |
Dozer, 1.2m3 bucket, 50-200m2, Sand/Soil | 43.5 | 48.0 | 52.6 | m3/hr |
Dozer, 1.2m3 bucket, over 200m2, Sand/Soil | 55.5 | 61.1 | 66.7 | m3/hr |
Dozer, 1.2m3 bucket, 50-200m2, Gravel | 43.8 | 48.3 | 52.9 | m3/hr |
Dozer, 1.2m3 bucket, over 200m2, Gravel | 55.5 | 61.1 | 66.7 | m3/hr |
Dozer, 1.2m3 bucket, 50-200m2, Hardcore | 37.1 | 40.3 | 43.5 | m3/hr |
Dozer, 1.2m3 bucket, over 200m2, Hardcore | 47.6 | 51.6 | 55.6 | m3/hr |
Dozer, 1.2m3 bucket, 50-200m2, Boulder Clay | 43.8 | 45.7 | 47.6 | m3/hr |
Dozer, 1.2m3 bucket, over 200m2, Boulder Clay | 55.6 | 59.1 | 62.5 | m3/hr |
- Category: Excavation
- Hits: 66218
Planning and Estimating Production Rates
Task / Description | Slow | Ave | Fast | Units |
Hydraulic Excavator, 0.3m3 bucket, Sand/Soil | 5.6 | 7.1 | 8.2 | m3/hr |
Hydraulic Excavator, 0.3m3 bucket, Gravel Beds | 4.8 | 6.1 | 7.3 | m3/hr |
Hydraulic Excavator, 0.3m3 bucket, Clay/Chalk | 4.8 | 6.1 | 7.1 | m3/hr |
Hydraulic Excavator, 0.3m3 bucket, Hard Ground | 9.7 | 5.4 | 6.4 | m3/hr |
Hydraulic Excavator, 0.4m3 bucket, Sand/Soil | 20.5 | 25.0 | 29.2 | m3/hr |
Hydraulic Excavator, 0.4m3 bucket, Gravel Beds | 18.2 | 22.2 | 26.0 | m3/hr |
Hydraulic Excavator, 0.4m3 bucket, Clay/Chalk | 18.2 | 22.2 | 26.0 | m3/hr |
Hydraulic Excavator, 0.4m3 bucket, Hard Ground | 17.0 | 20.0 | 23.4 | m3/hr |
Hydraulic Excavator, 0.5m3 bucket, Sand/Soil | 26.0 | 28.6 | 33.1 | m3/hr |
Hydraulic Excavator, 0.5m3 bucket, Gravel Beds | 26.3 | 28.6 | 33.2 | m3/hr |
Hydraulic Excavator, 0.5m3 bucket, Clay/Chalk | 26.3 | 28.6 | 33.2 | m3/hr |
Hydraulic Excavator, 0.5m3 bucket, Hard Ground | 22.7 | 25.0 | 28.8 | m3/hr |
Excavate and Board Trench, 0.5-1.5m deep, < 2.0m wide | 3.3 | 4.5 | 6.8 | m2/hr |
Excavate and Board Trench, 1.5-3.0m deep, < 2.0m wide | 3.0 | 4.2 | 6.5 | m2/hr |
Excavate and Board Trench, 3.0-4.5m deep, < 2.0m wide | 2.7 | 4.0 | 6.0 | m2/hr |
Excavate and Board Trench, 0.5-1.5m deep, > 2.0m wide | 6.6 | 7.1 | 8.8 | m2/hr |
Excavate and Board Trench, 1.5-3.0m deep, > 2.0m wide | 6.2 | 6.7 | 9.2 | m2/hr |
Excavate and Board Trench, 3.0-4.5m deep, > 2.0m wide | 5.8 | 6.2 | 10.5 | m2/hr |
- Category: Excavation
- Hits: 23285
Planning and Estimating Production Rates
/ Description | Slow | Ave | Fast | Units |
Hydraulic Excavator, 0.3m3 bucket, Sand/Soil - Basement Works | 6.4 | 8.0 | 9.4 | m3/hr |
Hydraulic Excavator, 0.3m3 bucket, Gravel Beds - Basement Works | 5.5 | 6.9 | 8.1 | m3/hr |
Hydraulic Excavator, 0.3m3 bucket, Clay/Chalk - Basement Works | 5.2 | 6.5 | 7.9 | m3/hr |
Hydraulic Excavator, 0.3m3 bucket, Hard Ground - Basement Works | 4.7 | 5.9 | 8.2 | m3/hr |
Hydraulic Excavator, 0.4m3 bucket, Sand/Soil - Basement Works | 12.6 | 15.4 | 18.9 | m3/hr |
Hydraulic Excavator, 0.4m3 bucket, Gravel Beds - Basement Works | 11.7 | 14.3 | 16.7 | m3/hr |
Hydraulic Excavator, 0.4m3 bucket, Clay/Chalk - Basement Works | 10.9 | 13.3 | 15.6 | m3/hr |
Hydraulic Excavator, 0.4m3 bucket, Hard Ground - Basement Works | 9.7 | 11.8 | 14.0 | m3/hr |
Hydraulic Excavator, 0.5m3 bucket, Sand/Soil - Basement Works | 18.2 | 20.0 | 23.0 | m3/hr |
Hydraulic Excavator, 0.5m3 bucket, Gravel Beds - Basement Works | 16.5 | 18.1 | 20.0 | m3/hr |
Hydraulic Excavator, 0.5m3 bucket, Clay/Chalk - Basement Works | 15.4 | 16.7 | 19.3 | m3/hr |
Hydraulic Excavator, 0.5m3 bucket, Hard Ground - Basement Works | 13.3 | 15.4 | 17.7 | m3/hr |
- Category: Excavation
- Hits: 38203
Planning and Estimating Production Rates
Task / Description | Slow | Ave | Fast | Units |
Excavation Bulking Factor, Sand/Soil | - | 15.0 | 20.0 | % |
Excavation Bulking Factor, Gravel | - | 33.0 | - | % |
Excavation Bulking Factor, Clay/Chalk | - | 40.0 | - | % |
Excavation Bulking Factor, Boulder Clay | - | 45.0 | - | % |
Excavation Bulking Factor, Rock | - | 60.0 | - | % |
Spoil Weight, Rock | - | 2.5 | - | Tonnes/m3 |
Spoil Weight, Concrete | - | 2.4 | - | Tonnes/m3 |
Spoil Weight, Landfill/CDG | - | 1.9 | - | Tonnes/m3 |
Spoil Weight, Sand | - | 1.8 | - | Tonnes/m3 |
Rail Mounted Grab, 2.0m3 bucket 2.4min lift cycle | 30.0 | 48.0 | 59.0 | m3/hr |
Crane Mounted Clamshell Grab, 2.0m3 bucket 2.9min lift cycle | 25.0 | 33.0 | 41.0 | m3/hr |
Crane Mounted Clamshell Grab, 2.5m3 bucket 2.9min lift cycle | 34.0 | 42.0 | 52.0 | m3/hr |
Hydraulic Excavator, 0.3m3 bucket, Sand/Soil | 6.9 | 8.7 | 10.2 | m3/hr |
Hydraulic Excavator, 0.4m3 bucket, Sand/Soil | 23.4 | 28.6 | 33.4 | m3/hr |
Hydraulic Excavator, 0.5m3 bucket, Sand/Soil | 45.5 | 50.0 | 58.0 | m3/hr |
Hydraulic Excavator, 0.3m3 bucket, Gravel Beds | 5.6 | 7.1 | 8.2 | m3/hr |
Hydraulic Excavator, 0.4m3 bucket, Gravel Beds | 20.5 | 25.0 | 29.0 | m3/hr |
Hydraulic Excavator, 0.5m3 bucket, Gravel Beds | 36.8 | 40.0 | 46.0 | m3/hr |
Hydraulic Excavator, 0.3m3 bucket, Clay/Chalk | 5.6 | 7.1 | 8.3 | m3/hr |
Hydraulic Excavator, 0.4m3 bucket, Clay/Chalk | 20.5 | 25.0 | 28.7 | m3/hr |
Hydraulic Excavator, 0.5m3 bucket, Clay/Chalk | 37.0 | 40.0 | 46.0 | m3/hr |
Hydraulic Excavator, 0.3m3 bucket, Hard Ground | 4.5 | 6.1 | 7.2 | m3/hr |
Hydraulic Excavator, 0.4m3 bucket, Hard Ground | 17.9 | 22.2 | 25.0 | m3/hr |
Hydraulic Excavator, 0.5m3 bucket, Hard Ground | 25.7 | 28.6 | 32.9 | m3/hr |