⚠️Resource Table Structure:
- Section Header Level 1 - Is normally split into two buckets Assemblies and Accounting Packages:
- Assemblies: This heading should only have Complex Resources allocated to it (NB The Assemblies Section Total should have a value of Nil)
- Accounting Package Headings: Labour, Plant, Material, Consumables and Subcontractors etc.
- Section Level 2 and beyond: Are for additional detail, the user can continue to break down his Resources into unlimited accounting groups.
⚠︎ Example of the Resource Section Headers structure:
- Assemblies > Cartage: Aggregate cartage < 15 minutes - 10t per load @ 6.86 per tonne
- Labour > Direct Labour: Carpenter @ 28.47 per hour
- Materials > Watermains > Pipes: 100mm PN9 x 6.0m uPVC Pipe @ 9.09 per meter
- Consumables > Plant: Diesel @ 1.02 per liter
- Subcontractors > Civils: Drainage @ 1.00 sum (open the worksheets select the subbie resource, then enter the subcontractor price in the equation field)
Set Resource Section Levels:
- Select the range of items below the resource you wish to convert into a Resource Heading
- Then use the Context menu or the Application Toolbar to indent the selected items.
- This converts the Resource Line Item into a Resource Header
For worksheet pricing, we need to create some resources. The Resource Types have already been defined above.