Construction Man-hour Norms
Description | Unit | Tradesman Hours | Labourer Hours | |
Grid Suspended Ceilings | Suspension Systems, suspended 600mm from | |||
concrete soffit or steel purlins | ||||
Fully concealed suspension system | m2 | 0.2 | ||
Exposed grid system | m2 | 0.18 | ||
Linings | ||||
10mm plasterboard fixed to concealed suspension | m2 | 0.25 | ||
system | ||||
Plasterboard tiles set into exposed grid system | m2 | 0.14 |