Estimating Productivity of Concrete Demolition
* Production rates listed are based on 8-hr shift. The above figures are for general estimation purpose only and must not be used to guarantee any production figure to the customer. The actual working results may vary according to the quality and structure of the material to be broken, required degree of material size reduction, installation, condition of the carrier, conditions at the worksite, haulage of the broken material, skills of the operator etc.
Task / Description | Slow | Ave | Fast | Units |
Hammer (2,200lb - 1,000kg) - 315C Excavator | ||||
Non-Reinforced Concrete | 150cu.yd - 115m3 | 200cu.yd - 153m3 | 375cu.yd - 287m3 | cu.yd & m3/8hr |
Reinforced Concrete | 140cu.yd - 107m3 | 160cu.yd - 122m3 | 240cu.yd - 184m3 | cu.yd & m3/8hr |
Sedimentary Rock | 165cu.yd - 126m3 | 200cu.yd - 153m3 | 300cu.yd - 229m3 | cu.yd & m3/8hr |
Volcanic Rock | 75cu.yd - 57m3 | 110cu.yd - 84m3 | 150cu.yd - 115m3 | cu.yd & m3/8hr |
Hammer (3,740lb - 1,700kg) - 330C Excavator | ||||
Non-Reinforced Concrete | 275cu.yd - 210m3 | 375cu.yd - 287m3 | 490cu.yd - 375m3 | cu.yd & m3/8hr |
Reinforced Concrete | 200cu.yd - 153m3 | 150cu.yd - 115m3 | 350cu.yd - 268m3 | cu.yd & m3/8hr |
Sedimentary Rock | 250cu.yd - 191m3 | 150cu.yd - 115m3 | 400cu.yd - 306m3 | cu.yd & m3/8hr |
Volcanic Rock | 135cu.yd - 103m3 | 150cu.yd - 115M3 | 275cu.yd - 210m3 | cu.yd & m3/8hr |
Hammer (6,946lb - 3,150kg) - 345C Excavator | ||||
Reinforced Concrete | 300cu.yd - 229m3 | 385cu.yd - 295m3 | 850cu.yd - 650m3 | cu.yd & m3/8hr |
Sedimentary Rock | 350cu.yd - 268m3 | 440cu.yd - 337m3 | 900cu.yd - 688m3 | cu.yd & m3/8hr |
Volcanic Rock | 200cu.yd - 153m3 | 275cu.yd - 210m3 | 600cu.yd - 459m3 | cu.yd & m3/8hr |
Demolishing Reinforced & Unreinforced Concrete - manual jack hammer
Task / Description | Slow | Ave | Fast | Units |
Concrete Slabs, unreinforced 50-150mm | 3.2 | - | 1.9 | hrs/m3 |
Concrete Slabs, unreinforced 150-300mm | 5.5 | 4.1 | 3.7 | hrs/m3 |
Concrete Slabs, reinforced 50-150mm | 5.2 | - | 3.9 | hrs/m3 |
Concrete Slabs, reinforced 150-300mm | 9.1 | 6.2 | 4.7 | hrs/m3 |
Concrete Walls, unreinforced | 4.7 | 3.9 | 3.1 | hrs/m3 |
Concrete Walls, reinforced | 5.6 | 4.7 | 3.9 | hrs/m3 |
Concrete Foundations, unreinforced | 3.6 | 3.3 | 3.0 | hrs/m3 |
Concrete Foundations, reinforced | 5.4 | 5.1 | 4.8 | hrs/m3 |
Concrete Beams | 7.5 | 6.5 | 5.6 | hrs/m3 |
Concrete Columns | 9.2 | 8.2 | 7.3 | hrs/m3 |
Tarmac paving 20-50mm thick | 1.9 | 1.7 | 1.5 | hrs/m3 |
Tarmac paving 50-100mm thick | 2.1 | - | 1.6 | hrs/m3 |
Tarmac paving 100-150mm thick | 2.1 | - | 1.7 | hrs/m3 |
Tarmac roadway 150mm thick | - | 3.6 | - | hrs/m3 |
Brickwork, walls and columns | 2.4 | 1.8 | 1.3 | hrs/m3 |
Brickwork, foundations | 2.7 | 2.1 | 1.5 | hrs/m3 |
Cutting Back Piles & Slabs - Manual Jack Hammer
Task / Description | Slow | Ave | Fast | Units |
Concrete Pile Caps, 50-300mm deep and 0.6m dia | 0.6 | - | 0.3 | hrs/no |
Concrete Pile Caps, 300-750mm deep and 0.6m dia | 1.5 | - | 0.4 | hrs/no |
Concrete Pile Caps, > 750mm deep and 0.6m dia | 1.8 | - | 0.8 | hrs/no |
Concrete Pile Caps, 50-300mm deep and 1.1m dia | 1.9 | - | 0.8 | hrs/no |
Concrete Pile Caps, 300-750mm deep and 1.1m dia | 2.5 | - | 1.1 | hrs/no |
Concrete Pile Caps, > 750mm deep and 1.1m dia | 4.2 | - | 2.3 | hrs/no |
Concrete Pile Caps, 50-300mm deep and 2.5m dia | 9.2 | - | 8.2 | hrs/no |
Concrete Pile Caps, 300-750mm deep and 2.5m dia | 10.1 | - | 9.5 | hrs/no |
Concrete Pile Caps, > 750mm deep and 2.5m dia | 11.5 | - | 10.2 | hrs/no |
Concrete, Cutting Slabs, 5-25m deep | - | 15.2 | - | m/hr |
Concrete, Cutting Slabs, 25-50m deep | - | 11.5 | - | m/hr |
Concrete, Cutting Slabs, 50-75m deep | - | 6.7 | - | m/hr |
Concrete, Cutting Holes, coring machine | - | 0.2 | - | m3/hr |
Concrete, Cutting Back to expose couplers 0.7m slab | - | 2.5 | - | m/day |