Demolition Estimating Man-hours
Description | Structure | Unit | Tradesman Hours | Labourer Hours |
Floors | ||||
Remove vinyl floor tiles or carpet | m2 | 0.2 | ||
Break up and remove concrete floor topping | ||||
100mm thick | m2 | 1.00 | ||
150mm thick | m2 | 1.50 | ||
Scabble concrete to receive new screed | m2 | 0.2 | ||
Walls | ||||
Demolish | ||||
Single skinned masonry wall | m2 | 0.5 | ||
Timber framed partly glazed plasterboard wall | m2 | 0.3 | ||
Remove ceramic wall tiles on solid plaster, make good to | m2 | 1.00 | ||
receive paint finish | ||||
Cut and form opening in single skin masonry wall for single | No | 7.00 | ||
door, including teething and bonding, and making good to render | ||||
Roofing/Ceilings | ||||
Take down suspended ceiling system | m2 | 0.3 | ||
Remove asphalt roofing, make good | m2 | 1.00 |
Demolition Production Rates
Task / Description | Slow | Ave | Fast | Units |
Weight, Structural Steel | - | 2.5 | - | Tonnes/m3 |
Remove & Cart away, Ceramic Wall Tiles | 2.0 | 2.5 | 3.4 | m2/hr |
Remove & Cart away, Wallpaper, 1 layer | - | 8.7 | - | m2/hr |
Remove & Cart away, Wallpaper, 2 layers | - | 7.1 | - | m2/hr |
Remove & Cart away, Wallpaper, 3 layers | - | 5.7 | - | m2/hr |
Remove & Cart away, Lathe and Plaster Ceilings | 3.2 | 4.6 | 5.0 | m2/hr |
Remove & Cart away, Plaster to Walls | 2.1 | 3.1 | 5.9 | m2/hr |
Remove & Cart away, External Render | - | 3.9 | - | m2/hr |
Remove & Cart away, Floor Screed | - | 3.2 | - | m2/hr |
Remove & Cart away, Concrete Paving | - | 4.0 | - | m2/hr |
Remove & Cart away, Brickwork Walls, 1.0 brick thick | - | 1.3 | - | m2/hr |
Remove & Cart away, Brickwork Walls, 0.5 brick thick | - | 2.6 | - | m2/hr |
Remove & Cart away, Brickwork Walls, Sand/Lime Mortar | - | 1.8 | - | hrs/100 |
Remove & Cart away, Fireplace and Hearth | - | 1.9 | - | hrs/no |
Remove & Cart away, Floor Boards | - | 6.2 | - | m2/hr |
Remove & Cart away, Skirting, Architrave, Dado rail etc | - | 16.5 | - | m/hr |
Remove & Cart away, Staircase | - | 7.3 | - | hrs/no |
Remove & Cart away, Windows, 0-1m2 | - | 0.6 | - | hrs/no |
Remove & Cart away, Windows 1-2m2 | - | 0.8 | - | hrs/no |
Remove & Cart away, Windows 2-3m2 | - | 0.9 | - | hrs/no |
Remove & Cart away, Doors | - | 0.3 | - | hrs/on |
Remove & Cart away, Door Frame | - | 0.1 | - | hrs/no |
Remove & Cart away, Floor and Ceiling Joists | - | 1.1 | - | hrs/m |
Remove & Cart away, Wall Plates | - | 3.9 | - | hrs/m |
Remove & Cart away, Iron Bath | - | 1.4 | - | /hrs/no |
Remove & Cart away, Wash Basin/Sink | - | 0.8 | - | /hrs/no |
Remove & Cart away, Pipework including brackets etc | - | 6.1 | - | m/hr |