Retaining structures

Get Started

Planning and Estimating Production Rates

Task / Description Slow Ave Fast Units
Rule of Thumb, overall rate by Mill 0.5 1.1 1.2 hrs/no
Fabricate reinforcement cages - 4.0 - hrs/cage
Concreting barrette panels 40.0 50.0 55.0 m3/hr
Trimming top of barrette panels - 2.4 - days/no
Concrete Testing, Coring Test 4.0 3.5 2.0 days/no
Concrete Testing, Sonic Logging Test - 0.7 - days/no

 

Customer feedback counts

The Experts

Client Reviews

  GoodFirms Badge   Crozdesk   Methvin is a leader in Construction Estimating on G2  Login   Vinci   Holder   Hoar