- Category: Tower Cranes
- Hits: 15603
Planning Production Rates
Task / Description | Slow | Ave | Fast | Units |
Erect and Setup 50m gib | - | 11.0 | 7.5 | days |
Dismantle 50m gib | - | 10.0 | - | days |
Lifting, Reinforcement Bins and Cages, 1st 15m lift | - | 3.2 | - | mins/lift |
Lifting, Reinforcement Bins and Cages, above 1st 15m lift | - | 0.5 | - | mins/15m |
Lifting, Crane Tracking Time | - | 3.3 | - | seconds/m |