Task / Description Slow Ave Fast Units
Windows, Timber Frames for Bricklaying 1.1 0.5 0.1 hrs/no
Windows, Drill, Screw & Plug extra over 0.3 0.1 - hrs/no
Door Frames, Softwood, 1.0-3.0m2 - 0.2 - hrs/no
Door Frames, Softwood, 3.0-7.0m2 0.5 0.4 - hrs/no
Door Frames, Softwood, 7.0-10.0m2 1.2 0.8 - hrs/no
Door Frames, Hardwood, 1.0-3.0m2 - 0.3 - hrs/no
Door Frames, Hardwood, 3.0-7.0m2 0.6 0.3 - hrs/no
Door Frames, Hardwood, 7.0-10.0m2 1.4 1.0 - hrs/no
Erect Water Tank Platform - 2.3 - no/hr
Fix Studding For Bath - 0.1 - hrs/m
Cut Access Hatch - 0.3 - no/hr
Floor Joists, under 3m 9.0 9.6 11.6 no/hr
Floor Joists, 3.0-4.5m 6.8 7.2 9.7 no/hr
Floor Joists, 4.5-6.0m 5.5 5.8 7.3 no/hr
Ceiling Joists, under 3m 12.8 14.0 14.7 no/hr
Ceiling Joists, 3.0-4.5m 10.8 12.1 12.6 no/hr
Ceiling Joists, 4.5-6.0m 9.6 10.8 11.1 no/hr
Ceiling Joists, Notch to Beams 20.0 25.0 28.5 no/hr
Ceiling Joists, Pack Joist Ends 20.1 23.8 26.3 no/hr
Ceiling Joists, Nailing Joists together - 23.0 - m/hr
Ceiling Joists, Bolting Joists Together - 12.6 - m/hr
Floor Boards, Butt Jointed - 1.7 - m2/hr
Floor Boards, T&G Boards, under 75mm wide - 3.4 - m2/hr
Floor Boards, T&G Boards, 75-100mm wide - 3.8 - m2/hr
Floor Boards, T&G Boards, 100-125mm wide - 4.2 - m2/hr
Floor Boards, T&G Boards, 125-150mm wide - 5.5 - m2/hr
Plywood Sheeting, Butt Jointed, nailed - 9.1 10.2 m2/hr
Plywood Sheeting, Butt Jointed, screwed - 4.1 4.8 m2/hr
Plywood Sheeting, T&G Jointed, nailed - 8.3 9.1 m2/hr
Plywood Sheeting, T&G Jointed, screwed - 4.0 4.6 m2/hr
Chipboard Sheeting, Butt Jointed, nailed - 10.0 11.5 m2/hr
Chipboard Sheeting, Butt Jointed, screwed - 5.1 5.8 m2/hr
Chipboard Sheeting, T&G Jointed, nailed - 9.3 9.1 m2/hr
Chipboard Sheeting, T&G Jointed, screwed - 5.5 5.9 m2/hr