Concrete Work

 

Concrete Finishing Estimating Man-hours

Description Tasks Unit    Tradesman Hours Labourer Hours
 Surface Finishes        
  Hand Trowel m2   0.15
  Power Float m2   0.18
  Broomed Finish m2   0.12

 

Concrete Finishing Production Rates

Task / Description Slow   Ave   Fast    Units
 Surface Finishing, Steel Float By Hand 9.2  13.9  25.0   m2/hr
 Surface Finishing, Wood Float By Hand 11.7  17.2  29.4   m2/hr
 Surface Finishing, Power Float 13.9  20.8  37.0   m2/hr
 Surface Finishing, Light Brush on Trowel 55.8  90.1  170.0   m2/hr
 Surface Finishing, Brush on Trowel Margin 28.8  48.5  85.0   m2/hr
 Surface Finishing, Sprayed By Pump, expose aggregate 65.0  95.0  145.0   m2/hr
 Surface Finishing, Wire Brush, expose aggregate 15.0  25.0  30.0   m2/hr
 Making Good Walls, prepare, shutter, pour -   5.5  8.6   m2/hr
 Making Good Columns, prepare, shutter, pour -   2.8  6.9   m2/hr
 Making Good Sides of Beams, prepare, shutter, pour -   2.8  7.0   m2/hr
 Making Good Slab Soffits, prepare, shutter, pour -   4.2  5.5   m2/hr
 Making Good Bolt Holes, prepare, shutter, pour 14.8  16.8  25.8   no/hr
 Making Good Rubdown Precast Concrete, prepare, shutter, pour -   18.0  -    m2/hr
 Making Good Scabble 3 head brush hammer, prepare, shutter, pour 30.7  59.5  73.8   hrs/m2