Surface Finishes

Get Started

Concrete Finishing Estimating Man-hour Norms

Description Tasks Unit    Tradesman Hours Labourer Hours
 Surface Finishes        
  Hand Trowel m2   0.15
  Power Float m2   0.18
  Broomed Finish m2   0.12

 

Concrete Finishing Planning Production Rates

Task / Description Slow Ave Fast Units
Surface Finishing, Steel Float By Hand 9.2 13.9 25.0 m2/hr
Surface Finishing, Wood Float By Hand 11.7 17.2 29.4 m2/hr
Surface Finishing, Power Float 13.9 20.8 37.0 m2/hr
Surface Finishing, Light Brush on Trowel 55.8 90.1 170.0 m2/hr
Surface Finishing, Brush on Trowel Margin 28.8 48.5 85.0 m2/hr
Surface Finishing, Sprayed By Pump, expose aggregate 65.0 95.0 145.0 m2/hr
Surface Finishing, Wire Brush, expose aggregate 15.0 25.0 30.0 m2/hr
Making Good Walls, prepare, shutter, pour - 5.5 8.6 m2/hr
Making Good Columns, prepare, shutter, pour - 2.8 6.9 m2/hr
Making Good Sides of Beams, prepare, shutter, pour - 2.8 7.0 m2/hr
Making Good Slab Soffits, prepare, shutter, pour - 4.2 5.5 m2/hr
Making Good Bolt Holes, prepare, shutter, pour 14.8 16.8 25.8 no/hr
Making Good Rubdown Precast Concrete, prepare, shutter, pour - 18.0 - m2/hr
Making Good Scabble 3 head brush hammer, prepare, shutter, pour 30.7 59.5 73.8 hrs/m2

Customer feedback counts

The Experts

Client Reviews

  GoodFirms Badge   Crozdesk   Methvin is a leader in Construction Estimating on G2  Login   Vinci   Holder   Hoar