Pile Cutting Back
Task / Description Slow   Ave   Fast    Units
 Concrete Pile Caps, 50-300mm deep and 0.6m dia 0.6  -   0.3   hrs/no
 Concrete Pile Caps, 300-750mm deep and 0.6m dia 1.5  -   0.4   hrs/no
 Concrete Pile Caps, > 750mm deep and 0.6m dia 1.8  -   0.8   hrs/no
 Concrete Pile Caps, 50-300mm deep and 1.1m dia 1.9  -   0.8   hrs/no
 Concrete Pile Caps, 300-750mm deep and 1.1m dia 2.5  -   1.1   hrs/no
 Concrete Pile Caps, > 750mm deep and 1.1m dia 4.2  -   2.3   hrs/no
 Concrete Pile Caps, 50-300mm deep and 2.5m dia 9.2  -   8.2   hrs/no
 Concrete Pile Caps, 300-750mm deep and 2.5m dia 10.1  -   9.5   hrs/no
 Concrete Pile Caps, > 750mm deep and 2.5m dia 11.5  -   10.2   hrs/no
 Concrete, Cutting Slabs, 5-25m deep -   15.2  -    m/hr
 Concrete, Cutting Slabs, 25-50m deep -   11.5  -    m/hr
 Concrete, Cutting Slabs, 50-75m deep -   6.7  -    m/hr
 Concrete, Cutting Holes, coring machine -   0.2  -    m3/hr
 Concrete, Cutting Back to expose couplers 0.7m slab -   2.5  -    m/day