Rail Trackwork

Planning and Estimating Production Rates

/ Description Slow Ave Fast Units
FST Floating Track Slab, side restraints 9.6 - - m/day
FST Floating Track Slab, resin pads 10.2 - - m/day
FST Floating Track Slab, slab units 10.6 - - m/day
PCBT - Pre-cast Concrete Block Track, in Bored Tunnels 17.1 41.0 - m/day
PCBT - Pre-cast Concrete Block Track, in Cut and Cover Tunnels - 35.0 - m/day
PCBT - Pre-cast Concrete Block Track, in Station Tunnels - 35.0 - m/day
IST - Isolated Slab Track, in Bored Tunnels - 20.0 - m/day
IST - Isolated Slab Track, in Cut and Cover Tunnels - 34.0 - m/day
IST - Isolated Slab Track, in Station - 29.0 - m/day
FST - Floating Slab Track, in Station 3.6 4.6 5.7 m/day
Ballasted Track, in Mainline 57.0 71.0 115.0 m/day
Ballasted Track, in Depot - 28.0 - m/day
Non-Ballasted Track, in Depot 8.5 12.8 17.4 m/day
Embedded / Paved Track, in Depot - 71.0 - m/day
Heavy Maintenance / Train Wash Track, in Depot - 29.0 - m/day
Maintenance Pit, in Depot - 52.0 - m/day
Siding Trackwork, in Depot - 38.0 - m/day