Stonework

Get Started

Planning Production Rates

Task / Description Slow Ave Fast Units
Fix 0.5m2 Stones to Metal Support Frame 5.6 7.0 7.8 m2/day
Fix 0.5-0.75m2 Stones to Metal Support Frame 7.2 9.0 10.1 m2/day
Fix 0.75-1.0m2 Stones to Metal Support Frame 6.9 8.7 9.7 m2/day
Fix Complex Stonework to Metal Support Frame - 1.8 - m2/day
Fix Curved Stone Cladding 6.9 8.0 9.2 m2/day
Fix Stone Edge Beams/Window Reveals - 2.3 3.2 m2/day
Fix Stone Soffits - 4.0 - m2/day
Stone Floors 6.9 10.4 12.2 m2/day
Granite Wall Panels, First Fix - 1.3 - m2/hr
Granite Wall Panels, Second Fix - 1.1 - m2/hr