Metal Decking

Planning and Estimating Production Rates

Task / Description Slow Ave Fast Units
Metal Decking, large areas - 70.0 - m2/day
Metal Decking, small or complicated - 28.0 - m2/day
Titanium Sheeted Roofs - 9.5 - m2/day
Copper Roofs, flat work - 3.0 - m2/day
Copper Roofs, sloping work - 2.7 - m2/day
Zinc Roofs, flat work - 2.4 - m2/day
Zinc Roofs, sloping work - 2.1 - m2/day
Aluminium Roofs, flat work - 2.8 - m2/day
Aluminium Roofs, sloping work - 1.9 - m2/day
Lead Roofs, flat work - 2.5 - m2/day
Lead Roofs, sloping work - 2.1 - m2/day
Lead Roofs, dormer cheeks - 1.3 - m2/day
Lead Roofs, flat gutters - 88.0 - m/day
Lead Roofs, flat copings - 76.0 - m/day
Lead Roofs, stepped gutters - 3.5 - m/day
Lead Roofs, shaped copings - 3.3 - m/day
Lead Roofs, cover step flashings - 3.2 - m/day
Lead Roofs, rooflight flashings - 0.8 - no/day
Lead Roofs, domed roof coverings - 0.7 - m2/day