Available work area < 60,000m2
m2
Working width < 40m
m
Location Rural = 1.0 Small City = 0.85 Big City = 0.75
%
Major pavement items Production Rate Unit
Lime-Treated Sub-grade 0 m2/d
Subbase production rate 0 m3/d
Basecource production rate 0 m3/d
Finishing basecource production rate 0 m2/d
Hot Mix Asphalt Base 0 Ton
Hot Mix Asphalt Surface 0 Ton
Concrete Paving 0 m2/d

These production rates are a good rule of thumb for the construction of Basecourse

 Urban environment:

Spread & Compact Production = 30m3/hr

Trimming Production = 250m2/hr

 

Rural environment:

Spread & Compact Production = 50m3/hr

Trimming Production = 350m2/hr