Road and Rail

Prep for Kerbs and Slabs

Task / Description Slow   Ave   Fast    Units
 Concrete Road surfacing, Kerbs or Side Haunches -   0.4  -    m3/hr
 Concrete Road surfacing, 150mm thick -   12.5  -    m2/hr
 Concrete Road surfacing, 200mm thick -   7.7  -    m2/hr
 Concrete Road surfacing, 300mm thick -   6.7  -    m2/hr

 

Kerb and Concrete Slab Production Rates

Task / Description Slow   Ave   Fast    Units
 Concrete Slabs, laid on bedding, to slight falls 2.7  -   4.2   m2/hr
 Concrete Slabs, laid on bedding, to steep falls 2.3  -   2.7   m2/hr
 Concrete Slabs, laid in mortar, to slight falls 1.5  -   2.3   m2/hr
 Concrete Slabs, laid in mortar, to steep falls 1.1  -   1.5   m2/hr
 Concrete Slabs, laid on sand, to slight falls 1.7  -   2.8   m2/hr
 Concrete Slabs, laid on sand, to steep falls 1.6  -   1.9   m2/hr
 Cobble Stones, laid in mortar, no patterns -   0.3  -    m2/hr
 Cobble Stones, laid in mortar, with patterns -   0.2  -    m2/hr
 Artificial Stone, laid on sand, with patterns -   2.5  -    m2/hr
 Brick Paviors, in mortar, straight joints 0.9  1.3  1.9   m2/hr
 Brick Paviors, in mortar, herringbone pattern -   1.0  1.2   m2/hr
 Gravel Paths, including preparation of sub-base -   10.5  -    m2/hr
 Concrete Paths, 100mm thick, including preparation of sub-base -   2.5  -    m2/hr
 Concrete Kerbs or Channels, laid straight -   6.2  -    m/hr
 Concrete Kerbs or Channels, laid to 5m radius -   4.5  -    m/hr
 Concrete Kerbs or Channels, laid to 10m radius -   5.0  -    m/hr
 Concrete Kerbs or Channels, laid to 20m radius -   5.5  -    m/hr
 Stone/Granite Kerbs or Channels, laid straight -   3.5  -    m/hr
 Concrete Edging, laid straight -   7.7  -    m/hr
 Concrete Edging, laid to 5m radius -   5.8  -    m/hr
 Concrete Edging, laid to 10m radius -   6.2  -    m/hr
 Concrete Edging, laid to 20m radius -   7.1  -    m/hr
 Cutting and Fitting Ends, Concrete Kerbs -   6.6  -    no/hr
 Cutting and Fitting Ends, Channels -   5.8  -    no/hr
 Cutting and Fitting Ends, Concrete Edging -   8.3  -    no/hr