- Category: Kerbs & Footpaths
- Hits: 24033
Planning and Estimating Production Rates
Prep for Kerbs and Slabs
Task / Description | Slow | Ave | Fast | Units |
Concrete Road surfacing, Kerbs or Side Haunches | - | 0.4 | - | m3/hr |
Concrete Road surfacing, 150mm thick | - | 12.5 | - | m2/hr |
Concrete Road surfacing, 200mm thick | - | 7.7 | - | m2/hr |
Concrete Road surfacing, 300mm thick | - | 6.7 | - | m2/hr |
Kerb and Concrete Slab Production Rates
Task / Description | Slow | Ave | Fast | Units |
Concrete Slabs, laid on bedding, to slight falls | 2.7 | - | 4.2 | m2/hr |
Concrete Slabs, laid on bedding, to steep falls | 2.3 | - | 2.7 | m2/hr |
Concrete Slabs, laid in mortar, to slight falls | 1.5 | - | 2.3 | m2/hr |
Concrete Slabs, laid in mortar, to steep falls | 1.1 | - | 1.5 | m2/hr |
Concrete Slabs, laid on sand, to slight falls | 1.7 | - | 2.8 | m2/hr |
Concrete Slabs, laid on sand, to steep falls | 1.6 | - | 1.9 | m2/hr |
Cobble Stones, laid in mortar, no patterns | - | 0.3 | - | m2/hr |
Cobble Stones, laid in mortar, with patterns | - | 0.2 | - | m2/hr |
Artificial Stone, laid on sand, with patterns | - | 2.5 | - | m2/hr |
Brick Paviors, in mortar, straight joints | 0.9 | 1.3 | 1.9 | m2/hr |
Brick Paviors, in mortar, herringbone pattern | - | 1.0 | 1.2 | m2/hr |
Gravel Paths, including preparation of sub-base | - | 10.5 | - | m2/hr |
Concrete Paths, 100mm thick, including preparation of sub-base | - | 2.5 | - | m2/hr |
Concrete Kerbs or Channels, laid straight | - | 6.2 | - | m/hr |
Concrete Kerbs or Channels, laid to 5m radius | - | 4.5 | - | m/hr |
Concrete Kerbs or Channels, laid to 10m radius | - | 5.0 | - | m/hr |
Concrete Kerbs or Channels, laid to 20m radius | - | 5.5 | - | m/hr |
Stone/Granite Kerbs or Channels, laid straight | - | 3.5 | - | m/hr |
Concrete Edging, laid straight | - | 7.7 | - | m/hr |
Concrete Edging, laid to 5m radius | - | 5.8 | - | m/hr |
Concrete Edging, laid to 10m radius | - | 6.2 | - | m/hr |
Concrete Edging, laid to 20m radius | - | 7.1 | - | m/hr |
Cutting and Fitting Ends, Concrete Kerbs | - | 6.6 | - | no/hr |
Cutting and Fitting Ends, Channels | - | 5.8 | - | no/hr |
Cutting and Fitting Ends, Concrete Edging | - | 8.3 | - | no/hr |