Construction Man-hour Norms
Description | Sub Floor Framing | Unit | Tradesman Hours | Labourer Hours |
Jack stud | 100mm x 100mm | m | 0.22 | |
Bearer | 100mm x 75mm | m | 0.22 | |
125mm x 100mm | m | 0.24 | ||
Joist | 150mm x 50mm | m | 0.2 | |
200mm x 50mm | m | 0.21 | ||
250mm x 50mm | m | 0.22 | ||
300mm x 50mm | m | 0.22 | ||
Solid blocking | 100mm x 50mm | m | 0.17 | |
150mm x 50mm | m | 0.23 | ||
200mm x 50mm | m | 0.25 | ||
300mm x 50mm | m | 0.32 | ||
Beam | 200mm x 50mm | m | 0.23 | |
250mm x 50mm | m | 0.28 | ||
200mm x 100mm | m | 0.29 | ||
300mm x 100mm | m | 0.36 |