Water Proofing

Get Started

Construction Man-hour Norms

Task / Description Slow   Ave   Fast    Units
 Asphalt coatings, horizontal surfaces 3.5  4.2  5.8   m2/hr
 Asphalt coatings, vertical surfaces 1.2  1.7  2.2   m2/hr
 Bituminous Brushed application, 2 coats 4.8  5.0  6.3   m2/hr
 Bituminous Brushed application, 3 coats 3.3  3.5  4.4   m2/hr
 Bituminous Sheets, horizontal surfaces 3.8  4.0  4.8   m2/hr
 Bituminous Sheets, vertical surfaces 3.3  3.5  4.2   m2/hr
 Polythene Sheets, horizontal surfaces -   20.0  -    m2/hr
 Bentonite Sheets, horizontal surfaces 18.7  25.0  31.3   m2/hr
 Bentonite Sheets, vertical surfaces 11.2  15.0  17.3   m2/hr
 Epoxy Based application, 1 coat -   75.0  -    m2/hr
 Epoxy Based application, 2 coat -   38.0  -    m2/hr

 