Excavate and Remove

Planning and Estimating Production Rates

Task / Description Slow Ave Fast Units
Excavate Spoil Heaps to Transport, 0.6m3 bucket, Sand/Soil 14.5 20.0 25.6 m3/hr
Excavate Spoil Heaps to Transport, 0.6m3 bucket, Gravel Beds 15.2 20.4 25.6 m3/hr
Excavate Spoil Heaps to Transport, 0.6m3 bucket, Clay/Chalk 12.3 18.5 23.2 m3/hr
Excavate Spoil Heaps to Transport, 0.6m3 bucket, Boulder Clay 11.2 16.9 21.3 m3/hr
Excavate Spoil Heaps to Transport, 1.1m3 bucket, Sand/Soil 25.4 30.3 35.7 m3/hr
Excavate Spoil Heaps to Transport, 1.1m3 bucket, Gravel Beds 25.6 31.3 37.0 m3/hr
Excavate Spoil Heaps to Transport, 1.1m3 bucket, Clay/Chalk 22.5 27.8 33.3 m3/hr
Excavate Spoil Heaps to Transport, 1.1m3 bucket, Boulder Clay 18.9 24.4 30.3 m3/hr
Load Spoil to Barge, capacity 2,000m3 - 8.0 - hrs
Load Spoil to Barge, capacity 1,500m3 - 6.5 - hrs
Load Spoil to Barge, capacity 1,000m3 - 5.5 - hrs
Spoil conveyor, 600mm belt, 150m/min - 260.0 - m3/hr