Basement Excavation

Planning and Estimating Production Rates

/ Description Slow Ave Fast Units
Hydraulic Excavator, 0.3m3 bucket, Sand/Soil - Basement Works 6.4 8.0 9.4 m3/hr
Hydraulic Excavator, 0.3m3 bucket, Gravel Beds - Basement Works 5.5 6.9 8.1 m3/hr
Hydraulic Excavator, 0.3m3 bucket, Clay/Chalk - Basement Works 5.2 6.5 7.9 m3/hr
Hydraulic Excavator, 0.3m3 bucket, Hard Ground - Basement Works 4.7 5.9 8.2 m3/hr
Hydraulic Excavator, 0.4m3 bucket, Sand/Soil - Basement Works 12.6 15.4 18.9 m3/hr
Hydraulic Excavator, 0.4m3 bucket, Gravel Beds - Basement Works 11.7 14.3 16.7 m3/hr
Hydraulic Excavator, 0.4m3 bucket, Clay/Chalk - Basement Works 10.9 13.3 15.6 m3/hr
Hydraulic Excavator, 0.4m3 bucket, Hard Ground - Basement Works 9.7 11.8 14.0 m3/hr
Hydraulic Excavator, 0.5m3 bucket, Sand/Soil - Basement Works 18.2 20.0 23.0 m3/hr
Hydraulic Excavator, 0.5m3 bucket, Gravel Beds - Basement Works 16.5 18.1 20.0 m3/hr
Hydraulic Excavator, 0.5m3 bucket, Clay/Chalk - Basement Works 15.4 16.7 19.3 m3/hr
Hydraulic Excavator, 0.5m3 bucket, Hard Ground - Basement Works 13.3 15.4 17.7 m3/hr